Council Land Use Action to rezone a parcel of land from NR3 (Neighborhood Residential 3) to LR2 (M) (Lowrise 2 (M)). Project includes 2, 3-story apartment buildings (53 units total). Parking for 11 vehicles proposed. Clerk File #314491
View Design Proposal (9 MB)
Project Milestones
-
Neighborhood Outreach
completed
[process] 2/11/2020 - Revised 8/20/2021
Record Number: 006300-19PA
The applicant is conducting neighborhood outreach with communities near this project to share information about the development and to gather community input on local context and future development.
-
Early Design Guidance
active
[process] 2/7/2020 - Revised
Record Number: 3036071-EG
SDCI is reviewing the project site, proposed development, and early design concepts for the conceptual design using the adopted design guidelines.
-
Land Use Application Review
completed
[process] 3/16/2022 - Revised 12/23/2024
Record Number: 3036119-LU
SDCI has received the application and is conducting reviews to make sure it meets our land use code. This application may include a public notice and comment period.
This project may need additional design and architectural analysis, and environmental (SEPA), geotechnical, and zoning reviews.
-
Land Use Decision/Recommendation
completed
Published 12/23/2024 - Revised
Record Number: 3036119-LU
SDCI has published a land use decision or recommendation on whether the project meets the requirements of the Seattle Municipal Code. An appeal period follows this publication date.
-
Land Use Permit
future
Issued - Revised
SDCI has issued the land use permit. The project can now start applying for any required construction permits.
-
Construction Application Review
future
[process] - Revised
SDCI has received the application and is conducting reviews to make sure it meets our codes and requirements.
Note: When there are multiple construction permits on a project, it is possible for one construction permit to be issued while another construction application review at the same address is in progress. To view all permit activity, see Project Records and Documents below.
-
Construction Permit
future
Issued - Revised
SDCI has issued the building permit and construction may begin.
Note: When there are multiple construction permits on a project, it is possible for one construction permit to be issued while another construction application review at the same address is in progress. To view all permit activity, see Project Records and Documents below.
-
Construction Completed
future
- Revised
All construction work has finished. If this step is active, then only final paperwork is keeping this project open.
Project Records and Documents
006300-19PA Building & Land Use Pre-Application
3036071-EG Early Design Guidance